Application Overview PDF Brochure
System III Moisture Barrier, Beneath Slab Waterproofing
THREE BARRIERS IN ONE TOUGH COMPOSITE SYSTEM

Features

• Excellent Tensile Strength – The result of the unique field installed Composite Design.

• Cost Effective – The material costs and installation-speed make this a high value, quality, and performance solution.

• Seamless Installation – Fluid applied component makes the transition detailing and field a seamless installation.

• Fully Bonded With Slab – The geotextile surface of the barrier mechanically interlocks with the concrete slab to form a permanent bond between the barrier and the slab.

• Redundant Protection – Multiple waterproofing barriers and protection courses.


Approvals: City of Los Angeles, Research Report #25478 for waterproofing.

The Components:

BASE MEMBRANEECOSHIELD-P

An extremely tough, non-degrading laminated sheet good that comes in 10’x200’ rolls for easy installation with a minimum of seams that provides a substrate for the liquid membrane.


MIDDLE MEMBRANEECOLINE-S

A spray-applied, high-build, exceptionally flexible, monolithic membrane that is the pliable, bonding gasket in the system.


TOP MEMBRANE – ECOSHIELD-PP

A puncture and abrasion resistant fabric and film laminate that protects the other components from other construction damage and bonds to the concrete slab.


Step 1

Step 2

Step 3

Step 4
The Installation Steps:

Step 1. – BASE BARRIER

• Lay ECOSHIELD in one direction with six-inch overlaps.
• Treat both sides of overlap with ECOLINE-S or ECOLINE-R and compress with a roller.

Step 2. – DETAILING

• Treat all penetrations by applying a base coat of ECOLINE-S or ECOLINE-R in a 6-inch radius on the substrate around the penetration and 6-inches up on the penetrating object.
• Embed the polyester fabric into the base coat and apply a second coat of ECOLINE-S or ECOLINE-R, ensuring the fabric is completely saturated and covered.

Step 3. – MIDDLE BARRIER

• Begin spray application of ECOLINE-S from the lowest point on horizontal plane.
• Spray application pattern should be in 4’x4’ passes to achieve desired millage.

Step 4. – TOP BARRIER

• Lay ECOSHIELD in opposite direction of the base membrane installation.
• Treat overlaps in same fashion as base course.
• Terminate to exterior perimeter substrate by turning a six-inch flap up and applying ECOLINE-S or ECOLINE-R to the flap and substrate and then attaching a termination bar to the flap and substrate or apply a coat of ECOLINE-R 3” on each side of the seam and embed 6” polyester into this coat and apply a second coat of ECOLINE-R.